Power your home. Not your electricity bill.
On-grid rooftop solar sized from your own JBVNL bill. We register you on the PM Surya Ghar portal, deal with the electricity department, and stay with you until the subsidy reaches your bank account.
The site visit is completely free — no visiting fee, no hidden charges. You decide only after you've seen our written proposal.
A 3 kW system: about 11–12 units / day on the yearly average, anywhere in Jharkhand
Is your home a good fit for solar?
Start with your bill, not a package. JBVNL charges domestic units in slabs, so the units you replace with solar are the expensive ones at the top of your bill. A home using 200–500 units a month usually gets the strongest payback. A home using under 100 units still saves, but more slowly — we will tell you that honestly before you sign anything.
Roof space. Plan on roughly 60 sq ft of open, shade-free roof for every 1 kW. A 3 kW system needs about 180 sq ft. Water tanks, stair rooms and a neighbour's taller building all cast shade, so we check the roof in person.
What the electricity department allows. Your system cannot be larger than your sanctioned load, and all the solar on your local transformer is capped at 15% of its capacity. This transformer limit is the most common reason applications are cut back in Jharkhand. We check it with the local sub-division before we file your application.
Generation. Across Jharkhand, each 1 kW produces about 3.8 units a day on the yearly average: around 4.5 in January–March, and 2.5–3.4 in July–September under monsoon cloud. We size on your district’s conservative figure and show the monsoon dip up front, so it does not surprise you. See the figures for your district.
One person accountable, start to finish
We coordinate the whole job. You are never the one chasing JBVNL.
A written proposal before you pay
The full installed price, what is included, what is not, and the subsidy you can expect. Anything that could change the price is listed on the same page.
ALMM-listed equipment, vetted installers
Panels and inverters from the government ALMM list — non-ALMM equipment gets the subsidy rejected. Installation is done by partner teams we have checked, and our name is on the outcome.
Portal, electricity department and net meter
PM Surya Ghar registration, JBVNL feasibility, inspection, the bi-directional net meter and the subsidy claim. We track every step and tell you what is pending.
Manufacturer warranties, in writing
Panel performance warranties are the manufacturer’s — typically 25 years. We explain the terms before you sign and keep the paperwork on file for you.
A written proposal before you pay
The full installed price, what is included, what is not, and the subsidy you can expect. Anything that could change the price is listed on the same page.
ALMM-listed equipment, vetted installers
Panels and inverters from the government ALMM list — non-ALMM equipment gets the subsidy rejected. Installation is done by partner teams we have checked, and our name is on the outcome.
Portal, electricity department and net meter
PM Surya Ghar registration, JBVNL feasibility, inspection, the bi-directional net meter and the subsidy claim. We track every step and tell you what is pending.
Manufacturer warranties, in writing
Panel performance warranties are the manufacturer’s — typically 25 years. We explain the terms before you sign and keep the paperwork on file for you.
Running in about a month. Subsidy about 25–30 days later.
Most of the wait is the electricity department. Here is who is responsible at each step.
- 1
Free site visit and bill check
We look at your roof, shade, sanctioned load and the last few bills.
⏱️ Within a week · Solar Center
⏱️ Within a weekSolar Center - 2
Written proposal
System size, equipment, full price and expected subsidy — in writing.
⏱️ 2–3 days · Solar Center
⏱️ 2–3 daysSolar Center - 3
Portal registration and electricity-department feasibility
We register you on pmsuryaghar.gov.in and apply to JBVNL. JBVNL may approve a smaller size.
⏱️ 7–21 days · JBVNL
⏱️ 7–21 daysJBVNL - 4
Installation
A vetted partner team installs ALMM-listed equipment. We check the work.
⏱️ 1–3 days on site · Installation partner, supervised by Solar Center
⏱️ 1–3 days on siteInstallation partner, supervised by Solar Center - 5
Inspection and net meter
JBVNL inspects the system and fits the bi-directional meter. Net metering starts from the next bill.
⏱️ 25–30 days · JBVNL
⏱️ 25–30 daysJBVNL - 6
Subsidy in your bank account
We upload the commissioning papers. The central subsidy is paid directly to your account.
⏱️ 25–30 days · MNRE
⏱️ 25–30 daysMNRE